Bathroom Remodeling Contractor in Columbus, Ohio


Hall baths, primary suites and new baths built where there was none — waterproofing tested and inspected before anything gets covered.

Bathroom Remodeling · Columbus, Ohio

This page is for Columbus homeowners planning a bathroom remodel — a hall bath, a primary suite, or a new bath going in where there was none — who want a licensed general contractor to handle the whole job. We work in Columbus, Dublin, Upper Arlington, Hilliard, Westerville, Delaware and Powell.

Bathrooms are small, wet and dense. Plumbing, electrical, ventilation, waterproofing, tile and carpentry all occupy the same few square feet, and the mistakes that matter are the ones nobody sees again once the tile is on. We build the assembly in order and have it inspected before it is covered.

Bathrooms, like kitchens, are small enough that subcontracting every trade makes them expensive, so our own crew self-performs most of the work. Licensed plumbing, electrical and HVAC subcontractors come in when the layout or the mechanicals move; when they do not, our crew swaps the fixtures, vanity, lights and finishes without a subcontractor in the room. A small project wants a self-performing construction firm.

What a bath remodel can include

Not every bath needs a full gut. This is the range of the work; your written scope of work says which of it applies.

How we work

  1. A free first call Twenty to thirty minutes. We ask what the property is and roughly how big, which rooms are involved, rough dimensions, whether the electrical panel or the plumbing has ever been updated — by you or a previous owner — and who is supplying the finishes. With that and the age of the house (Columbus grows in rings from downtown, so the neighborhood usually tells us) we can put a realistic range on the job before anyone visits, and say honestly whether we are the right fit.
  2. On-site consultation or estimate A design consultation is $225 per hour, billed in 15-minute increments. A written project estimate is a one-time $125, and that estimate fee is credited toward the project if you contract with us; consultation time is billed as work performed.
  3. Scope, selections and contract We write the scope of work, the fixture and finish schedule and the allowances. Pricing depends on the contract and the scope. Work our own crew performs is billed time and materials at our published hourly rates, with nothing added on top of the rate. Subcontracted trades are billed cost-plus: their documented cost plus a stated 20 percent fee. The estimate is built from the averages of the work we have performed, so it is a relatively accurate number, with finish selections carried as variable items. The deposit at signing is set per job — special-order items, quantity-priced materials and the size of the project decide it. We also talk contingencies up front: a small framing budget is set aside so rot found at the toilet flange, in the shower corners or around a window is priced and fixed without stopping the job. Financing up to $30,000 is available through our payment portal, subject to credit approval.
  4. Permits and pre-construction A like-for-like bath does not need a permit; moved plumbing or new circuits do. Plumbing review is handled by a different authority depending on where you live, so when one is needed we confirm the jurisdiction first, file the applications, and set the schedule and site rules with you before demolition. During demolition we install zone shut-off valves so the rest of the house keeps its water for the length of the job.
  5. Construction and close-out Weekly progress photos, progress invoices, typically weekly as the work completes, or a draw schedule written into the contract, inspections attended, and any permit finalled before the last invoice is issued.

What fails later

Most bathroom problems that surface two years on are waterproofing problems: a shower pan that was never flood-tested, a niche cut into a wet wall without a membrane behind it, an exhaust fan vented into the attic instead of through the roof. All three are cheap to do correctly while the wall is open and expensive to find afterwards. We test the pan, photograph the assembly, and have the rough-in inspected before anything is covered.

A typical bath, day by day

A gut remodel that keeps the layout — tub out, walk-in shower in, tile floor and surround — runs about like this. Days are working days.

That example — tub to walk-in shower, the bath expanded into a closet, tile floor and surround, galvanized drains replaced, finishes supplied by the owner — is a high-mid bath, not a luxury one: about 155 crew hours over just more than two weeks on site, roughly $21,000 plus the finish selections. The order is the same on every job — the FAQ walks through why.

The Highland bathroom before the remodel
Before
The Highland bathroom after the remodel
After

Recent projects

Questions we hear

How long does a bathroom remodel take?

A like-for-like bath — same layout, same mechanicals, no tile — is usually about a week on site. A gut remodel runs two to three weeks, four at the longest; the day-by-day above is a typical one at just over two. Adding a bathroom where none existed runs longer. You get a schedule at the pre-construction conference, not a number over the phone.

Who reviews the plumbing work?

It depends on the jurisdiction, which is the single most common point of confusion on central Ohio bathrooms. Columbus, Dublin, Westerville and Hilliard handle their own plumbing review. Upper Arlington goes through Franklin County Public Health. Delaware and Powell go through the Delaware General Health District. We confirm which applies to your address before filing.

Can we stay in the house during the work?

In almost every case, yes, as long as there is another working bathroom. We install zone shut-off valves during demolition so the rest of the house keeps its water while we work, isolate the work area and cover the path in and out.

How is the work priced?

Pricing depends on the contract and the scope. Work our own crew performs is billed time and materials at our published hourly rates, with nothing added on top of the rate. Subcontracted trades are billed cost-plus: their documented cost plus a stated 20 percent fee. The estimate is built from the averages of the work we have performed, so it is a relatively accurate number, with finish selections carried as variable items. The deposit at signing is set per job — special-order items, quantity-priced materials and the size of the project decide it. Every receipt and labor hour is recorded and available for your review.

What happens if you find rot?

We cannot always document it before pricing, so we talk about it before demolition and set aside a small framing budget in the estimate; it usually covers what we find. The usual spots are the toilet flange, the shower corners and the wall framing, and around a window if the bath has one. Anything beyond the budget is priced as a written change order before it is fixed.

Will someone from iSpec be there when the plumber is?

Yes. A project manager meets every subcontractor, lets them in and makes sure they have what they need; that is built into the estimate. If you would like one of us on site for the whole visit, that is scheduled and billed as project-management time.

Do you do whole-home renovations?

Yes. The Martin house and Chicago Avenue were whole-house gut remodels with new kitchens and baths inside them — see whole-home remodeling.

Start your project

Tell us what you are planning. We reply within one business day, and the first call is free.

Start your project See our bathroom work

Baths are often done alongside other work, so we also handle kitchen remodeling and home additions.